Examples of the work

Client work is confidential, so the examples below are demonstrations built with sample data. They show the format and the level of detail you would receive. Each one is labelled as a sample.

Executive dashboard

One screen for a programme director: performance indices, milestones at risk and package progress, with drill-down to the activities behind each figure. The version below is static sample data; the live build is interactive.

What a reader does with it

  • SPI 0.96 says the programme has earned 96% of what it planned to earn by the data date (61.4% complete against 64.0% planned, the same figures as the weekly report). The question for the meeting is which packages are driving it, which the package SPI column answers: Package B at 0.87 and fit-out at 0.70. The other packages are on or slightly ahead of their own plans.
  • CPI 1.02 says cost is slightly under plan for the work done. Combined with SPI below 1.0, the likely story is slower progress rather than overspend.
  • 1 milestone at risk links to the milestone register below, where it has an owner, a forecast date and a recovery action, and where a second milestone is on watch.

Schedule review findings

An extract from the findings table of an independent baseline review, built with sample data. The full report records every check against the contract requirements, with a recommendation and the evidence for each finding.

Sample findings table, sample data
RefFindingEffectRecommendationSeverity
F-0138 activities have no successor, including 6 on the structural worksCritical path is unreliable; float on structure is overstatedClose open ends; re-run the critical path before acceptanceHigh
F-02Procurement activities are not linked to the installation activities they feedLate deliveries will not move the installation dates in the scheduleAdd finish-to-start logic from delivery to first installation for each long-lead itemHigh
F-03Two calendars in use with different Friday working; MEP activities on the 7-day calendarMEP durations are understated by about 14%Confirm the agreed working week and apply one calendar per tradeMedium
F-04Testing and commissioning is a single 20-day activityNo visibility of system-by-system readiness for handoverBreak down by system; link each to its installation completionMedium
F-05Resource loading present for labour only; no equipment or costHistograms cannot support the cash flow submissionAdd cost loading at the agreed level before the first updateLow

Scroll the table sideways to see all columns.

Milestone register

An extract from a contract milestone register kept in a Power Apps tool, built with sample data and sharing the same sample programme and data date as the dashboard and the weekly report. Each row carries the contract date, the current forecast, the variance and the owner of the recovery action, and the app sends a reminder before each contractual notice date. Status: achieved, the milestone is complete; at risk, the forecast is later than the contract date and the milestone is on the critical path; on watch, the forecast is later than the contract date but float remains; on plan, the forecast is on or before the contract date.

Sample milestone register, sample data
MilestoneContract dateForecastVarianceStatusOwner
Enabling works complete15 Jun 202612 Jun 2026-3 daysAchievedEnabling works
Structure to level 1030 Sep 202621 Oct 2026+21 daysAt riskPackage B
Long-lead chillers delivered15 Nov 202615 Nov 20260On planProcurement
Facade watertight31 Dec 202614 Jan 2027+14 daysWatchPackage C

Scroll the table sideways to see all columns.

Weekly report extract

The first page of a weekly progress report for a contractor client, built with sample data. The figures are generated from the schedule update; the commentary is written by the planner.

Weekly progress reportWeek 38, data date 30 Sep 2026
Sample data

Summary

Overall progress 61.4% against 64.0% planned, 2.6 percentage points behind plan (SPI 0.96). The critical path runs through the level 10 structure, which is 21 days behind the contract milestone. A recovery programme has been issued for the engineer's review (ref. RP-03).

Critical path status

Structure to level 10 forecast 21 Oct 2026 against 30 Sep 2026. Cause: formwork crew reduced from three to two gangs in weeks 35 to 37. Recovery: third gang remobilised 28 Sep; forecast assumes the 6-day cycle is held.

Milestones

1 achieved, 1 at risk, 1 on plan, 1 on watch. See milestone register, rows 1 to 4.

Issues requiring the client's action

Approval of the chiller submittal (ref. SUB-114) is 9 days overdue. Each further week of delay moves chiller delivery, which is 12 days from the critical path.

Four-week lookahead

Level 11 and 12 slabs, start of facade bracket installation on the north elevation, MEP first fix levels 3 to 5.

Previous experience and references

The examples above are demonstrations. Our lead consultant has prepared and reviewed deliverables of this kind on capital projects in Saudi Arabia and the Gulf over more than 20 years; that is a personal professional record, not work contracted by Expert Systems. References for assignments contracted by Expert Systems will be published as they become available, with the client's consent. Until then we are happy to discuss relevant experience on a call.